New Window and Door Factory Extension, New Holland

CLIENT: HOWARTH TIMBER LIMITED

Project description

Works include a 5000m2 extension to the existing factory with an independent portal framed building on piled foundations and composite insulated cladding throughout.

The internal space is divided into production areas, final assembly and despatch. An internal two storey welfare and office block was also provided.

Externally a new entrance was formed onto Lincoln Castle Way, concrete paving for parking and access with associated drainage systems. A flood prevention wall was provided to protect the site.

The project was completed ahead of programme which allowed early access for the client internal fit out.



Project Details

Services Involved:

YOUR PROJECT

    Other Projects

    • New Warehouse
    • Autotrail, Europarc, Grimsby
    • Pigpro Egg Colony
    • New Bulk Store
    • New Winery & Machinery Building; Refurbishment & Conversion of Buildings
    • New Concrete Access Road