Autotrail, Europarc, Grimsby

CLIENT: AUTOTRAIL VR LIMITED

Project description

The project consisted of the construction of a 5500m2 steel framed and composite cladded extension to join two existing production buildings. The new extension provided additional production and storage areas with additional office and welfare facilities.

Building services include the extension of existing fire sprinkler system, new LED lighting to the extension and replacement LED fittings to existing buildings. A new rainwater harvesting system was provided to supply water to existing and new toilet facilities.

External works included approximately 22000m2 of concrete paving and associated drainage systems for parking vehicles. New security fencing and the forming of a new entrance to the extended site will also be provided.

Works were phased to maintain client's production throughout the 39 week programme.



Project Details

Services Involved:

YOUR PROJECT

    Other Projects

    • New Warehouse
    • Canada Dock, Liverpool
    • Structural Repairs to Jetty
    • New Builders Merchant Facilties, Northwich
    • Bespoke Home, Wressle
    • DFS - Kettering