New Steel Processing Building

CLIENT: C.F. BOOTH LTD

Project description

The project involved the design and construction of a 72 x 32 x 17 metre high building with 5 metre high concrete walls. The building was to be used for processing high value scrap metals with the perimeter concrete walls providing protection from the recycling process and security to the building.

12 metre high access roller shutter doors were provided to allow access for large processing equipment, 20 metre weighbridge was also installed within the building. Due to the high loads expected the insitu floor slab was constructed  traditionally reinforced 300mm thick concrete. The cladding system was composite throughout to reduce the risk of condensation.  Roof lights and vertical translucent sheets providing high levels of natural light in the building were installed.

A rainwater harvesting and attenuation system was incorporated using above ground storage tanks with syphonic drainage from the building. The project duration was 22 weeks.



Project Details

Services Involved:

YOUR PROJECT

    Other Projects

    • New Winery & Machinery Building; Refurbishment & Conversion of Buildings
    • Autotrail, Europarc, Grimsby
    • Warehouse Extension
    • New Bulk Store
    • Pigpro Egg Colony
    • New Warehouses, North Killingholme